EV Charger Installation for
Reseda Homeowners.
Level 2 charging on a dedicated 240V circuit. Adds 25-35 miles of range per hour. The standard for any home that drives the EV daily.
We work in Reseda regularly — on 1940s-1960s ranch homes — original 100A panels and knob-and-tube wiring still in service. Every EV charger installation job is permitted through the right authority (LADBS), built to NEC 2023, backed by a written workmanship warranty, and finished cleanly. The Alpha One Electric standard doesn’t change by city — only the local permit details do.
What’s Included.
- Load calculation on existing panel before quoting
- Dedicated 240V/50A circuit per NEC 625
- EV charger mounted at proper height
- Conduit run — EMT, rigid, or flex as routing requires
- NEMA 14-50 receptacle or hardwired connection
- GFCI breaker per NEC 2023
- Local electrical permit pulled and posted
- Title 24 compliance documentation
- LADWP rebate paperwork (where eligible — up to $1,000)
- Final inspection attended on-site
- Written workmanship warranty
Pricing & Timeline in Reseda.
Typical on-site duration: half a day to one full day. Total project schedule from your first call to a passed final inspection depends on the LADBS permit cycle — usually 1-3 weeks.
Reseda-Specific Considerations.
Reseda EV charger installation jobs route through LADBS for permits and inspections. We know the local rules, route to the right authority, and attend every inspection on-site. Reseda’s housing stock skews toward 1940s-1960s ranch homes — original 100A panels and knob-and-tube wiring still in service — we’ve worked on those types of properties extensively and know the patterns.
Why Alpha One Electric.
You get the owner on the phone, the owner walking your property, and the owner standing behind every wire we run. We use Siemens panels, Leviton Decora finish devices, Lutron dimmers and smart systems, and rigid steel conduit on exterior runs. We don’t install bargain-tier products. We pull every permit. We attend every inspection. We don’t leave a job until the city has signed off and you’re holding the documentation.